OIL, GAS & PETROCHEMICAL

Oil & Gas Lightning Protection, Earthing, Bonding & SPD

Lightning protection, static bonding, earthing and surge protection for refineries, LNG, LPG, CNG, tank farms and petrochemical facilities.

SN Engineering Scope
  • Site survey and data review
  • Risk-assessment support
  • Design, BOQ and material selection
  • Supply, installation, testing and AMC

Facilities and Assets Covered

Refineries and process units

Included in the project-specific lightning, earthing and surge-protection review.

LNG and LPG terminals

Included in the project-specific lightning, earthing and surge-protection review.

CNG and PNG stations

Included in the project-specific lightning, earthing and surge-protection review.

Tank farms and petroleum depots

Included in the project-specific lightning, earthing and surge-protection review.

Compressor and metering stations

Included in the project-specific lightning, earthing and surge-protection review.

Control rooms and substations

Included in the project-specific lightning, earthing and surge-protection review.

Loading gantries and pump houses

Included in the project-specific lightning, earthing and surge-protection review.

Why Protection Is Critical

Hazardous-area ignition risk

Requires dedicated engineering attention during risk assessment and detailed design.

Static bonding and equipotential control

Requires dedicated engineering attention during risk assessment and detailed design.

Corrosion and chemical exposure

Requires dedicated engineering attention during risk assessment and detailed design.

DCS, ESD, PLC and instrumentation protection

Requires dedicated engineering attention during risk assessment and detailed design.

Project-specific safety and approval requirements

Requires dedicated engineering attention during risk assessment and detailed design.

Sector Design Philosophy

The protection strategy should combine external lightning interception, down-conductor routing, earth termination, equipotential bonding and coordinated SPDs. The selected system must follow the current project specification, site conditions and authority requirements.

Engineering Design Workflow

1. Site Data

Collect drawings, dimensions, roof levels, coordinates, occupancy, critical equipment, hazardous classification and incoming services.

2. Risk Review

Evaluate strike exposure, local lightning activity, consequences of failure, fire risk, service continuity and project requirements.

3. System Selection

Select ESE or conventional IEC 62305 route only where accepted by the project specification.

4. External LPS

Define air termination, masts, down conductors, bonding and earth termination.

5. Internal Protection

Coordinate Type 1, Type 2 and signal-line SPDs with the electrical distribution and lightning protection zones.

6. Documentation

Prepare calculations, layouts, BOQ, technical specifications, method statement, test records and as-built drawings.

Typical BOQ

ItemDescriptionQuantity Basis
Air terminationESE terminal or conventional rods/mesh as specifiedCoverage and roof geometry
Mast/supportGI/SS mast, brackets, base or guyingMechanical and wind-load design
Down conductorSpecified conductor, holders and test jointsMeasured route and number of paths
EarthingElectrodes, conductors, chambers and bondingSoil study and earthing design
SPDsPower and signal-line surge protectionPanel and circuit survey
ServicesInstallation, testing, commissioning and documentationComplete project

Inspection, Maintenance and AMC

Visual Inspection

Check terminals, masts, conductors, joints, labels, supports, corrosion and mechanical damage.

Electrical Testing

Verify continuity, bonding, earth-system performance and SPD status using appropriate test methods.

Post-Strike Review

Inspect after a recorded event, severe storm, roof alteration or electrical modification.

AMC Documentation

Maintain inspection reports, earth-test records, event-counter readings, photographs and corrective-action BOQ.

Request a Technical Proposal

SN Engineering Project Support

Site survey, lightning risk assessment support, ESE or conventional system design, BOQ, material supply, installation, testing, commissioning and AMC.

Required inputs: site location, building dimensions, roof drawing, application, electrical single-line diagram, existing earthing and project specification.

Get ProposalWhatsApp